Construction Update July 2021

Hello to everyone!

As we all know, we have experienced incredibly challenging times yet again with COVID recently. Despite all this and as a big positive, we are happy to advise of some joy! Jubilee is progressing very well as we continue with our construction across the estate – this is something to celebrate!

Please see below our latest construction update:

JUBILEE

Stage completions:

– Stage 28 was completed earlier this year and titles issued in June

– Stage 21 has also completed and is now titled

– Stage 38 is currently being constructed and expect to finish in August

Stage commencements:

– Stage 36 is due to commence in August 21.

Landscaping:

Contractors have been engaged to build the 1ha park in Stage 20 at the junction of Welcome Parade and Millbrook Drive. Work is anticipated to start in early October and expected completion around March/April 2022.

Supermarket & shops: Works have commenced and builders are now on site. We are beyond excited with this! Estimated completion of this first stage is late 2022.

URBAN SQUARE

Stage commencement:

– Stages 50 & 51 (The first stages in our Urban Square Neighbourhood) are contracted to start in August 21. Stage 50 is scheduled to be delivered by mid- 2022.

Ison Rd Intersection:

– Construction of this signalised intersection is being managed by Dennis Family Corporation under supervision by Lotus Living. It is currently on track to be completed in March 2022 and will provide another gateway into Jubilee and Urban Square, opening up this area to a large employment/commercial area and the future Jubilee Central.

So things are moving along and we could not be more happier seeing more of Jubilee come to life. We have seen many more purchasers lately that will be calling Jubilee home in the future and that is so exciting!

 